Punta Catalina
COUNTRY

CLIENT

DESCRIPTION
720MW Thermoelectric plant composed of two boilers of approximately 12.000 tons of steel structures, turbines, large scale generators, desulfurization systems and a seaport for the coal delivery.
Emasa Engineering performed the complete definition of the erection strategy of the two boiler units, with viability studies and engineering projects for the modularization of steel structures (aiming schedule reduction through parallelism and safety improvement).
The strategy, based on the opening of access to the boiler cavity by one of the sides along with the modularization of large volumes of steel structure, allowed the client to keep up with the erection schedule, even with the intrinsic difficulty of access due to confined erection for the installation of members at higher elevations.
Beyond the constructability works, we also conducted procedures for the procurement of heavy load movement contractor, structural verifications, quality control of engineering and rigging plans.
Check Other Projects

The Tide Footbridge
Lifting engineering for the rotation and erection of plate-like modules with very irregular geometries for a landmark foot-bridge part of the large-scale renovation project of the Greenwich Peninsula Region.

Rio's Olympic Stadium Recovery
Analysis for the recovery of the roofing of the Olympic Stadium for the 2016 Rio de Janeiro Olympic games. The stadium, with its undulated roofing of an atypical arched structure, has a capacity for 47.000 spectators.

Corinthians Arena
Erection engineering, Heavy Lift analyses and connection peer review for the roofing. Large scale and very irregular steel modules where assembled, weighting up to 400Tons.

Bellara Steel Complex
Erection engineering for the installation of an Air Separation Unit with three large Coldboxes (weighting up to 160ton). Works included terrain and underground checks using FEA and a comprehensive site assistance campaign.


Tamoios Cable Crane
Structural engineering for the review of the cables and the supporting steel towers for a 20Ton cable crane system used in a highway construction. Advanced non-linear iterative FE procedures and dedicated codes were used for the cable’s analyses.

Punta Catalina
720MW Thermoelectric power plant comprised of two boilers weighing approximately 12.000 Tons of steel structures with large application of modularization. Erection studies performed also for turbines, generators, desulfurization systems and a seaport for the coal delivery.

Ethylene XXI
Implementation of modularization strategy for a 70m (230ft) multi-story industrial building and heavy lift verification for mechanical equipment weighting up to 900Tons.

Corinthians Arena - Mezzanine
Structural project of the north and south mezzanines of the Corinthians Stadium. The project weighing 400 Tons and with an area of 1800m2 has a complex support typology and holds the north and south large scale screens.

Corinthians Arena – Temporary Seats
Peer review and site inspection for the structures which supported the temporary seats for the stadium during the 2014 World Cup. The structure was a mixture of wide-flange profiles and scaffolding to accommodate 20.000 spectators.


Comperj
Structural and rigging verification of steel modules and chimney towers of the HRSG and Boiler of the UTL-11 plant.






.png)

